Overcoming Challenges
Wells provided time-saving advantages that helped overcome construction challenges and complete the $72.9 million space.
It was important to the design team that the panels visually expressed their exoskeleton nature of cladding the building. We collaborated with Wells and their engineers early in the process to push the envelope by minimizing the horizontal and vertical sections of concrete, maximizing window area, and beveling the openings and joints to create a seamless and uniform aesthetic. DAVID MILLERAIA, LEED AP, DESIGN PRINCIPAL, URBANWORKS ARCHITECTURE
Creating Success
Using a combination of lightly prestressed concrete and very intricate bent mesh and rebar, the Wells team manufactured large, cost-efficient acid-etch finish panels while still meeting the tower crane’s weight limit.
To meet the challenge of maintaining a watertight seal during construction, the Wells team developed an approach that protected critical joints and kept work moving efficiently. Once the prefabricated system was in place, our team completed exterior joint finishing to ensure long-term performance.
A precast enclosure system allowed us the ability to get the building enclosed much quicker than a conventional multi-layer, stick-built enclosure system would have. We were able to set an entire level of precast in five days; so every five days there was another floor that we could start interior construction on. KELLY MANSELLCONSTRUCTION EXECUTIVE, MORTENSON
The building reused the foundation walls remaining from the parking lot that once covered the site. 4Marq’s parking garage was placed on the seven floors above the lobby and is hidden by perforated panels. To improve cost-efficiency and eliminate the need for expensive mechanical ventilation, tinted two-layer anodized panels were placed to allow air to flow in from three sides.
The result is an elegant composition of precast that fit the budget, stayed on schedule, and achieved our design goals in an efficient and unique way. DAVID MILLERAIA, LEED AP, DESIGN PRINCIPAL, URBANWORKS ARCHITECTURE